Programmatic Agreement Among the National Park Service (U.S. Dept. of the Interior), the Advisory Council on Historic Preservation, and the National Conference of State Historic Preservation Officers
WHEREAS, the National Park Service (NPS) plans for, operates, manages, and administers the
National Park System, and is responsible for preserving, maintaining, and interpreting the cultural
resources of the System unimpaired for the enjoyment of future generations; and
WHEREAS, the operation, management, and administration of the System entail undertakings
that may affect historic properties (as defined in 36 CFR 800), which are therefore subject to
review under Sections 106, 110(f) and 111(a) of the National Historic Preservation Act as
amended (NHPA; 16 U.S.C. 470 et seq.) and the regulations of the Advisory Council on Historic
Preservation (Council) (36 CFR Part 800); and
WHEREAS, the NPS has established management policies, guidelines, standards, and technical
information designed for the treatment of cultural resources consistent with the spirit and intent of
the NHPA; and
WHEREAS, the NPS has a qualified staff of cultural resources specialists in parks, System
Support Offices, and archeological and preservation centers to carry out programs for cultural
resources; and
WHEREAS, the NPS has consulted with the National Conference of State Historic Preservation
Officers (Conference) and the Council regarding ways to ensure that NPS operation,
management, and administration of the System provide for management of the System's cultural
resources in accordance with the intent of NPS policies and with Sections 106, 110, and 111 of
the NHPA; and
WHEREAS, the National Park Service, the Conference, and the Council executed a Nationwide
Programmatic Agreement in 1990 that is superseded with the execution of this Programmatic
Agreement; and
WHEREAS, the NPS has restructured in order to place more resources and delegations of
authorities with park managers.
NOW, THEREFORE, the NPS, Conference, and Council mutually agree that the NPS will carry
out its Section 106 responsibilities with respect to management of the System in accordance with
the following stipulations:
STIPULATIONS
I. POLICY
The NPS will continue to preserve and foster appreciation of the cultural resources in its custody
through appropriate programs of protection, research, treatment, and interpretation. These
efforts are and will remain in keeping with the NHPA, the National Environmental Policy Act
(NEPA), the American Indian Religious Freedom Act, The Archaeological Resources Protection Act, the
Archeological and Historic Preservation Act of 1974, the Native American Graves Protection and
Repatriation Act, the Secretary of the Interior's Standards and Guidelines for Archeology and
Historic Preservation, NPS Management Policies, and the Guidelines for Federal Agency
Responsibilities Under Section 110 of the National Historic Preservation Act. It remains the NPS
goal to implement these programs in consultation with other Federal agencies, State Historic
Preservation Officers (SHPOs), Indian Tribes, local governments and the public.
Other guidelines, standards, and regulations relevant to this Agreement and its purposes include:
- NPS-28, Cultural Resource Management Guideline
- NPS-2, Planning Process Guideline
- NPS-6, Interpretation and Visitor Services Guideline
- NPS-12, NEPA Compliance Guideline
- NPS-38, Historic Property Leasing Guideline
- 36 CFR Part 18, Leases and Exchanges of Historic Property
II. IDENTIFYING CULTURAL RESOURCES
The NPS will coordinate with SHPOs activities for research related to resource management
needs and identification, evaluation, and registration of park historic properties. NPS fulfills these
responsibilities under Section 110 of the NHPA and 36 CFR Part 800.4, with regard to properties
potentially significant at national, State, or local levels and mindful of State preservation planning
and inventory programs.
III. DELEGATION OF AUTHORITY
- Park superintendents are the responsible agency officials as defined in 36 CFR Part 800.1(c) (1) (i) for purposes of Section 106 compliance. They will assume this responsibility in accordance with Stipulation VIII below.
- Superintendents will be held accountable for their performance in Section 106 compliance
through NPS procedures for performance and program evaluation.
- To meet this responsibility, each park will have the following:
- a commitment to training park staff, including an invitation to the appropriate SHPO and the Council to participate in that training, so that park staff are generally familiar with Section 106 processes; and
- at least one staff person qualified to act as the park's 106 coordinator, whose 106 responsibilities are specified in his or her position description and performance standards; and
- a formally designed set of CRM advisers whose qualifications are consistent with OPM standards, the intent of 36 CFR Part 61, Appendix A, and the intent of Section 112 (a) (1) (B) of the National Historic Preservation Act. Inpark staff, System Support Offices, other parks, NPS cultural preservation and archeological centers, Denver Service Center, other government agencies, and specialists and scholars outside NPS are all possible sources for needed expertise. Specialists who are not federal employees must meet the standards in 36 CFR Part 61, Appendix A.
- SHPOs and the Advisory Council may at any time raise with the appropriate Field
Director any programmatic or project matters where they wish the Field Director to review a park
superintendent's decision.
IV. PROJECT REVIEWNATIONWIDE PROGRAMMATIC EXCLUSIONS
- Undertakings listed in IV.B will be reviewed for Section 106 purposes within the NPS,
without further review by the Council or SHPOs, provided:
- that these undertakings are based upon information adequate to identify and
evaluate affected cultural resources [except for IV.B.(5)];
- that the NPS finds that their effects on cultural resources in or eligible for the
National Register will not be adverse based on criteria in 36 CFR Part 800.9; and
that decisions regarding these undertakings are made and carried out in conformity
with applicable policies, guidelines, and standards as identified in Stipulation I, and are
documented by NPS using the form for "Assessment of Actions Having and Effect on Cultural
Resources" or another appropriate format. (See Stipulation VII below.)
- The following undertakings may be reviewed under the terms of IV.A:
- preservation maintenance (housekeeping, routine and cyclic maintenance, and stabilization) as defined in NPS-28;
- routine grounds maintenance, such as grass cutting and tree trimming;
- installation of environmental monitoring units, such as those for water and air quality;
- archeological monitoring and testing and investigations of historic structures and cultural landscapes involving ground disturbing activities or intrusion into historic fabric for research or inventory purposes (see also Stipulations II and IX. C);
- acquisition of lands for park purposes, including additions to existing parks;
- rehabilitation and widening of existing trails, walks, paths, and sidewalks within previously disturbed areas;
- repaving of existing roads or existing parking areas within previously disturbed areas;
- placement, maintenance, or replacement of utility lines, transmission lines, and fences within previously disturbed areas;
- rehabilitation work limited to actions for retaining and preserving, protecting and maintaining, and repairing and replacing in kind materials and features, consistent with the Secretary of the Interior's Standards for Rehabilitation and the accompanying guidelines;
- health and safety activities such as radon mitigation, and removal of asbestos, lead paint, and buried oil tanks;
- installation of fire detection and suppression systems, and security alarm systems, and upgrading of HVAC systems;
- erection of signs, wayside exhibits, and memorial plaques;
- leasing of historic properties consistent with NPS-38, if proposed treatments are limited to those consistent with IV.B(1) and (9) and other activities excluded under IV.A and B.
- Park superintendents and SHPOs may develop additions to Stipulation IV.B that identify
other types of undertakings that they mutually agree will be excluded from further review.
Proposals for such additions will be provided for review to the Executive Director of the Council,
the NPS Director, and the Executive Director of the Conference. Upon their acceptance, the
Council, the Conference, and NPS will maintain records on those additions as amendments to this
Agreement, and provide for dissemination to other appropriate SHPOs and NPS offices.
- In the event that a SHPO questions whether a project should be considered a
programmatic exclusion under Stipulation IV. A and B, the superintendent and SHPO will make
every effort to resolve the issue informally. If those efforts fail, the question will be referred to
the Field Director. If the matter is still not resolved, it will be referred to the Advisory Council in
accordance with Stipulation XI.A.
V. PROJECT AND PROGRAM REVIEWOTHER UNDERTAKINGS
- All undertakings (as defined in 36 CFR Part 800), with the exception of those that meet
provisions in Stipulation IV, will be reviewed in accord with 36 CFR Part 800.
- Superintendents are encouraged to evaluate their park's program and discuss with SHPOs
ways to develop programmatic agreements for park undertakings that would otherwise require
numerous individual requests for comments.
- Memoranda of Agreement and Programmatic Agreements specific to a project, plan, or
park may be negotiated between park superintendents and SHPOs, pursuant to 36 CFR Part
800.5(e) or 800.13, and may be independent of or supplement this Agreement.
VI. RELATIONSHIP OF PROJECT REVIEW TO PLANS
- To the extent that the requirements of Section 106 and NEPA overlap for a given plan or
project, superintendents are encouraged to coordinate these two processes, including the
preparation of documentation and public involvement processes, in accordance with the guidance
in 36 CFR Part 800 or otherwise provided by the Advisory Council.
- In conformity with 36 CFR Part 800.3(c), park superintendents will ensure that the
Section 106 process is initiated early in the planning stages of any given undertaking, when the
widest feasible range of alternatives is open for consideration.
- General Management Plans (GMPs) establish a conceptual framework for subsequent
undertakings, and can thus play an important role in this process. GMPs may constitute the basis
for consultation under 36 CFR Part 800.4-6 on individual undertakings, if sufficient information
exists for resource identification, determination of National Register eligibility, and assessment of
the effect of a proposed undertaking on the property in question. In the absence of such
information, Section 106 consultation will normally be initiated or completed at subsequent stages
in the planning process [such as Development Concept Plans (DCPs) or other subsequent
implementing plans, as defined in NPS-2].
- The park superintendent will notify the appropriate SHPO and the Council when a GMP
or DCP is scheduled for preparation, amendment, revision, or updating. The superintendent will
request comments regarding preservation concerns relevant to the plan, such as management
objectives, identification and evaluation of historic properties, and the potential effects of
individual undertakings and alternatives on historic properties.
- During the planning process, the park superintendent, in consultation with the SHPO, will
make a determination about which undertakings are programmatic exclusions under IV.A and B,
and for all other undertakings, whether there is sufficient information about resources and
potential effects on those resources to seek review and comment under 36 CFR Part 800.4-6
during the plan review process. In cases where consultation is completed on specific
undertakings, documentation of this consultation will be included in the GMP or DCP.
- The approved plan will list all undertakings in the plan that are subject to further
consultation, and the stage of planning at which consultation is most likely to be completed.
- NPS GMPs will include a statement about the status of the park's cultural resources
inventory and will indicate needs for additional cultural resource information, plans, or studies
required before undertakings can be carried out.
VII. NPS PROCESS FOR DOCUMENTING ACTIONS HAVING AN EFFECT ON CULTURAL RESOURCES
All system-related undertakings that may have an effect on cultural resources will be appropriately
documented and carried out in accordance with applicable policies, guidelines, and standards, as
identified in Stipulation I. Formats for documentation include those outlined in published
Advisory Council guidance (see "Preparing Agreement Documents," for example), the NPS
"Assessment of Actions Having an Effect on Cultural Resources" forms, programmatic
agreements and, where appropriate, NEPA documentation that addresses cultural resources issues
with information consistent with requirements of 36 CFR Part 800.
Cultural resources specialists will review all such actions prior to their implementation, and parks
will maintain documentation of this review. Documentation of NPS reviews not already provided
to SHPOs and the Council will be available for review by the Council and the appropriate SHPO
upon request. Individual SHPOs who wish to review this documentation are responsible for
specifying scheduling, frequency, and types of undertakings of concern to them.
VIII. PUTTING THIS AGREEMENT INTO EFFECT
The delegation of Section 106 responsibility to park superintendents will take place as of October
1, 1995. As a condition of this delegation, each park will identify:
- the specialists, on or off park staff, who will provide the park with advice and technical services for cultural resource issues related to Section 106 compliance. These specialists must be qualified in their areas of expertise and have a specified term of commitment to advise the park; and
- a contact person to coordinate the park's Section 106 compliance processes.
Parks supplement on-staff expertise through advice and technical services from CRM specialists in
SSOs, the Denver Service Center, preservation centers, and other specified CRM specialists inside
and outside the NPS, for advice and technical services involved in responsible agency official for
106 purposes, who ensures the implementation of this agreement and 36 CFR Part 800
procedures, and who signs correspondence to SHPOs and the Advisory Council and
documentation of programmatic exclusions.
IX. COOPERATION AND COMMUNICATIONS
- Within six months of the date of the signature of this PA by all parties, and every two
years thereafter, each park superintendent will invite the appropriate SHPO(s) to meet to discuss
the compliance process and any actions necessary to improve communications between the park
and SHPO.
- SHPOs, the Conference, and the Council will be informed and consulted about revisions
to NPS standards and guidelines listed in Stipulation I.
- SHPOs, parks and NPS System Support Offices will share information about inventories
of historic properties, preservation planning processes, and historic contexts developed by each,
as well as other reports and research results related to cultural resources.
- SHPOs will treat the appropriate park superintendent as an interested party for purposes
of State environmental and preservation laws as they may relate to park undertakings and cultural
resources.
- The Council and SHPOs will treat the appropriate park superintendent as an interested
party under 36 CFR Part 800 for purposes of undertakings by other Federal agencies and Indian
tribes that may affect NPS areas, including undertakings in areas in and around parks.
- As required in NPS-2, NPS-12, the Section 110 Guidelines, and 36 CFR Part 800, NPS
will provide opportunities for Indian tribes and other interested persons to participate in the
processes outlined in this Agreement.
X. RELATIONSHIP TO OTHER EXISTING AGREEMENTS
- This Programmatic Agreement will become effective on October 1, 1995 and shall
supersede the following existing Programmatic Agreements:
- the Memorandum of Understanding executed in June 1976, regarding NPS planning documents;
- the Programmatic Memorandum of Agreement executed on December 19, 1979, and its amendments dated September 1981 and December 1985 regarding planning documents, energy management, and preservation maintenance;
- the Programmatic Memorandum of Agreement executed on December 19, 1982, regarding leasing of historic properties; and
- the nationwide Programmatic Agreement of 1990.
- Signature and implementation of this Agreement does not invalidate park-, Region-, or
project-specific Memoranda of Agreement or programmatic agreements negotiated for Section
106 purposes prior to the effective date of this Agreement.
XI. DISPUTE RESOLUTION
- Should a SHPO or the Council object to a park superintendent's decisions or actions
pursuant to any portion of this Agreement, the superintendent will consult the objecting party to
resolve the objection. If the park superintendent or the objecting party determines that the
objection cannot be resolved, the superintendent will forward all documentation relevant to the
dispute to the Field Director for further consultation. If the objection still cannot be resolved, the
Field Director will forward to the Council relevant documentation not previously furnished to the
Council. Within 30 days after receipt of all pertinent documentation, the Council will either:
- provide the Field Director with recommendations, which the Field Director will take into account in reaching a final decision regarding the dispute; or
- notify the Field Director that it will comment pursuant to 36 CFR Part 800.6(b), and proceed to comment. Any Council comment provided in response to such a request will be taken into account by the Field Director with reference to the subject of the dispute.
Any recommendation or comment provided by the Council will be understood to pertain only to
the subject of the dispute. The NPS responsibility to carry out all actions under this Agreement
that are not the subjects of the dispute will remain unchanged.
- When requested by any person, the Council will consider NPS findings under this
Agreement pursuant to the provisions of 36 CFR Part 800.6(e) on public requests to the Council.
XII. MONITORING, TERMINATION, AND EXPIRATION
- The National Park Service will convene a meeting of the parties to this Agreement on or
about November 15, 1996, to review implementation of the terms of this Agreement and
determine whether revisions or amendments are needed. If revisions or amendments are needed,
the parties will consult in accordance with 36 CFR Part 800.13.
- Any party to this Agreement may terminate it by providing ninety (90) days notice to the
other parties, provided that the parties will consult during the period prior to termination to seek
agreement on amendments or other actions that would avoid termination. In the event of
termination, the NPS will comply with 36 CFR Part 800 with regard to individual undertakings
otherwise covered by this Agreement.
ADVISORY COUNCIL ON HISTORIC PRESERVATION
By:____________________________________________Date:_____________
Chairman
NATIONAL PARK SERVICE
By:____________________________________________Date:_____________
Director
NATIONAL CONFERENCE OF STATE HISTORIC PRESERVATION OFFICERS
By:____________________________________________Date:_____________
President